August 30, 2005

Slabbing Away - Pics Attached

Picked the lads up at 7.45, we started on the hall, again more recess lights (5), it took a while, then onto the sitting rooms, 9 recess and a bay window meant it took us 2.5 hours!!
We then moved to the bedroom, was a flier, rapped it in an hour, then onto the dining room, six recess and 1 main light and a bay window killed us, spent literally all day doing the ceilings!!
Lads headed off at 7, I waited and finished the ensuite, totally finished now, have to complete the upstairs tomorrow regardless. Left at 11pm,
My dad installed the noggings for the manifold, 21 inches above the FFL.