I finished off the CAT6 cabling, finishing the runs to the bedroom downstairs and the 2nd bedroom upstairs.

I then decided to plumb the studded walls upstairs, each had to be plumbed and lathes run between them and the rafters to strenghten them, then screwed together, slow bleeding job!!

Insulation arrived today, sitting room is now filled to the hilt with rolls of rockwool for the walls and fibreglass for the roofspace.

I decided to source a mantlepiece and I think I have found what I am looking for, now to get a price!

Found http://www.wilsonsyard.com/ and this mantlepiece, and it sanded and waxed.

The also do a lovely gothic door, shame I did not spot these guys when we were looking!