September 06, 2005

Facia + Soffit

I picked Damo and Adam for 8am, there job was to finish the sun room and check all screws are in corretly and clean up the house.

No sign of John today, his 2 mates were there but enjoyed sitting in the cars instead of working!!!

The guttering company arrived today, they have all the soffit on, the facia on 2 gables and on the back, they also completed the whole of the 2 dormers, looks well!!

When I arrived for 6.30 dad was finishing the hall and Adam was finishing the sun room, it seems the sun louge took much longer than expected, whats new!!!

We set at it and got all the slabbing pulled downstairs, there is a strip to go all along the top of the stairs, around the landing.

I started to wheel out the rubbish slabs into a bunch, I also took the tools upstairs and filled the wardrobe with them!

The 2 lads headed off at about 9pm, it took me another 30 minutes or so to complete the stairs and clean up again.

It is excellent that there will be no more slabbing or insulation, good ridince!!!!!